Greens Slit Drainage
CTO designs and installs laser guided sub surface slit drainage systems into existing greens using our proven 6 step process:
- After consulting with the Project Manager/Superintendent the design is strategically mapped out to provide optimal drainage and playing conditions.
- The sod is cut cleanly and placed aside in the order it was removed.
- The collectors and slits are trenched using precision grade lasers to ensure accuracy.
- Slits are installed at a minimum depth of 12" and Collectors at a minimum of 14" to permit deep tine aerification practices without interference.
- The trenches are backfilled with a 60-20-20 mix (or mix of choice) and tamped in many lifts to ensure no settling.
- The turf is carefully replaced to the exact location from which it was removed and play can immediately resume upon completion. (approx. 2 days for an average size green start to finish)